SWIMMING POOL CELLAR SLAB CONCRETING COMPLETED , SHUTTERING & REINFORCEMENT WORKS IN PROGRESS FOR CELLAR SLAB OF CLUB HOUSE
BLOCK-B: BLOCK WORK COMPLETED UP TO 19TH FLOOR, INTERNAL PLASTER COMPLETED UP TO 17TH FLOOR & EXTERNAL PLASTER WORK IN PROGRESS FROM 19TH FLOOR TO GROUND
BLOCK-C: BLOCK WORK COMPLETED UP TO 18TH FLOOR & WORK IN PROGRESS AT 19TH FLOOR, INTERNAL PLASTER COMPLETED UP TO 15TH FLOOR & EXTERNAL PLASTER WORK IN PROGRESS