BLOCK-B: 3rd FLOOR SLAB CONCRETING COMPLETED ON 2nd DEC 2011
BLOCK-B: 4th FLOOR SLAB CONCRETING COMPLETED ON 25th DEC 2011
BLOCK-C: 1st FLOOR SLAB CONCRETING COMPLETED ON 3rd DEC 2011
BLOCK-C: 2nd FLOOR SLAB CONCRETING COMPLETED ON 27th DEC 2011
BLOCK-A: GROUND FLOOR SLAB CONCRETING COMPLETED ON 24th DEC 2011
BLOCK-D: CELLAR SLAB CONCRETING COMPLETED ON 29th DEC 2011
IN B/W BLOCKS B & C: SUB-CELLAR SLAB SHUTTERING & REINFORCEMENT WORK IN PROGRESS.
IN B/W BLOCK A&B: FOUNDATION WORKS IN PROGRESS
IN B/W BLOCK C&D: FOUNDATION EXCAVATION WORKS IN PROGRESS
IN B/W BLOCK C&D: FOUNDATION PCC WORKS IN PROGRESS
BLOCK-B; BLOCK WORK IN PROGRESS AT GROUND FLOOR & FIRST FLOOR.
BLOCK-B; 1ST COAT PLASTERING WORK IN PROGRESS AT GROUND & FIRST FLOOR.
BLOCK-C: BLOCK WORK AT GROUND FLOOR IN PROGRESS
BLOCK-C: BLOCK WORK & 1ST COAT PLASTERING WORK IN PROGRESS AT CELLAR.
BLOCK –B: ELECTRICAL CONDUITING WORKS AT GROUND & 1ST FLOOR IN PROGRESS.
BLOCK –B: ELECTRICAL GANG BOXES FIXING IN PROGRESS AT GROUND & 1ST FLOOR.