Gallery / Monthly Progress Photos. / June 2011

TOWER CRANE ERECTION IN PROGRESS

TOWER CRANE BOOM ERECTION IN PROGRESS

250 KVA TRANFORMER  INSTALLED  & CHARGED  ON 2ND JUNE 2011

325 KVA DG INSTALLED AND CHARGED AT SITE

SHUTTERING & REINFORCEMENT WORK IN PROGRESS FOR CELLAR SLAB OF BLOCK B

SUB-CELLAR  SLAB CONCRETING IN PROGRESS FOR BLOCK B

COLUMN (ABOVE CELLAR LVL) CONCRETING IN PROGRESS  IN BLOCK B

CELLAR SLAB BEAM SHUTTERING & RT.WALL SHUTTERING  IN PROGRESS FOR OF BLOCK B

FOOTING & COLUMN RCC  WORKS IN PROGRESS IN BLOCK A

RETAINING WALL RAFT RCC WORK IN PROGRESS- BLOCK A

FOOTING & COLUMNS RCC IN PROGRESS IN BLOCK C

RT.WALL RCC WORK IN PROGRESS  IN PROGRESS IN BLOCK C

FOOTING PCC & REINFORCEMENT  WORK IN PROGRESS IN BLOCK-D

RT .WALL RAFT RCC WORK IN PROGRESS IN BLOCK-D