BLOCK-B: 11th FLOOR SLAB CONCRETING COMPLETED ON 31st May 2012
BLOCK-A: 8th FLOOR SLAB CONCRETING COMPLETED ON 18th June 2012
BLOCK-C : 10th FLOOR SLAB CONCRETING COMPLETED ON 15th June 2012
BLOCK-D: 7th FLOOR SLAB CONCRETING COMPLETED ON 20th June 2012
BLOCK-B: BLOCK WORK COMPLETED UP TO 7TH FLOOR AND WORK IN PROGRESS AT 8TH & 9TH FLOOR, EXTERNAL PLASTER WORK IN PROGRESS
BLOCK-C: BLOCK WORK COMPLETED UP TO 5TH FLOOR AND WORK IN PROGRESS AT 6TH & 7TH FLOORS
BLOCK-A: BLOCK WORK COMPLETED UPTO 4TH FLOOR AND WORK IN PROGRESS AT 5TH FLOOR
BLOCK-D: BLOCK WORK COMPLETED UPTO 1ST FLOOR AND IN PROGRES AT 2ND & 3RD FLOOR.
EXTERNAL PLASTER IN PROGRESS AT BLOCK B GROUND TO 5TH FLOOR- SOUTH SIDE
STP WORKS: WALL CONCRETING COMPLETED AT BLOCK C
STROM WATER DRAIN WORK: RCC HUME PIPE LAYING WORK IN PROGRESS
IN B/W BLOCK C&D: CONCRETING OF RAMP AT CELLAR LEVEL COMPLETED